CONSULTING SERVICES
FEASIBILITY STUDY, DETAILED PLANING AND TENDERING, CONSTRUCTION SUPERVISION
Engineering services
comparable to HOAI phases 1-9
Client
Ministry of Public Works and Transport, Albania (AKUM)
Contractual relationship
Consortium
Processing period
2016-2023

Contact
Dr.-Ing. Helmfried Dietsch
Project Management
T +49 (0) 201 89 67-180
h.dietsch@dahlem-ingenieure.de
Shortdescription
The overall programme objective is to achieve improved and sustainable access of the population in the programme areas to safe drinking water at socially acceptable and cost-covering tariffs and adequate sanitation through sewerage disposal whilst performance of the utilities is improved.
The overall programme objective is to achieve improved and sustainable access of the population in the programme areas to safe drinking water at socially acceptable and cost-covering tariffs and adequate sanitation through sewerage disposal whilst performance of the utilities is improved.
Projectdata
The Specific Programme Objectives (SPO) of the MIP IV are defined as:
(i) Achieve a technically sustainable operation and maintenance cost coverage of water supply and sanitation infrastructure;
(ii) Extent the water supply hours from currently 2 to 4 hours to at least 12 h water supply (as already envisaged for the areas served by the MUN II project, however target value to be defined in FS);
(iii) Increase the collection efficiency concerning water bills;
(iv) Improve sewerage disposal by additional connections;
(v) Achieve social affordability of the water and sewerage tariffs;
The Programme consists of two parts:
Component Part A: Feasibility Study:
Phase 1: Preparatory Phase, Conceptual Project Planning, FS.
• Concept Design for sewage system: Proposal for short-, mid-, long-term investments 29 km collectors DN 250 – DN 2000, overflow structures and sewage pumping stations
• Conceptual Design of WWTP: 1st Stage (2030) 180,000 PE, 2nd Stage (2040) 248,000 PE
• Sludge Management Concept: Thermal/ Solar Drying Sludge Facilities (TSSDF) for 248,000 PE final horizon 2045, sludge output 6,179 t/a, and sludge mass reduction 69%
Component Part B: Project Implementation:
Phase 2: Detailed Design and Tender Preparation
Phase 3: Construction Phase
Phase 4: Defects Notification Phase
Under the Programme MIP IV water supply and sanitation measures were implemented:
2,25 km transmission water pipelines ductile iron DN400-500, 70 km water distribution network ductile iron and HDPE DN200 – DN400, 4,220 water supply house connections, 4 wells, 2 potable water chlorination facilities, 1 two story administration building, 0,1 km concrete DN 2000 sewage channel and 0,1 km concrete sewage channel DN 1500.