WWTP Heidenheim-Mergelstetten
New construction of digestion plant
Engineering services
Engineering structures, LPH 1-9
Technical equipment, LPH 1-9
Special services
- local construction supervision
Client
Stadt Heidenheim
Grabenstraße 15
89522 Heidenheim
Contractual relationship
Consortium
Processing period
Planning: 2017 - 2018
Construction: 2018 - 2021

Contact
Dr.-Ing. Anke Durth
Project Management
T +49 61 51 85 95-20
a.durth@dahlem-ingenieure.de
Shortdescription
At the Heidenheim-Mergelstetten wastewater treatment plant, sewage sludge was previously stabilized in two older digestion tanks. The city of Heidenheim therefore had a new digestion plant built.
Two digestion tanks with a volume of 1,400 m³ each, i.e. a total of 2,800 m³, were constructed. These were equipped in such a way that both single-stage and two-stage operation is possible. The tanks were designed as cylindrical reinforced concrete tanks with a flat sloping base.
A single-story machine room in solid construction with a steel stair tower was erected as a connecting building between the digestion tanks and the new thickener.
A new pipe channel was constructed to connect the new buildings to the process engineering system.
At the Heidenheim-Mergelstetten wastewater treatment plant, sewage sludge was previously stabilized in two older digestion tanks. The city of Heidenheim therefore had a new digestion plant built.
Two digestion tanks with a volume of 1,400 m³ each, i.e. a total of 2,800 m³, were constructed. These were equipped in such a way that both single-stage and two-stage operation is possible. The tanks were designed as cylindrical reinforced concrete tanks with a flat sloping base.
A single-story machine room in solid construction with a steel stair tower was erected as a connecting building between the digestion tanks and the new thickener.
A new pipe channel was constructed to connect the new buildings to the process engineering system.
Project data
- 130,000 PE
- New construction of two digestion tanks, V = 2 x 1,400 m³
- New construction of a post-thickener, V = 1,000 m³
- New construction of digestion plant machinery room
- New construction of stair tower
- New construction of pipe channel for connection to existing facilities
- Installation of an external sludge receiving station and a raw sludge pumping station in existing structures